The price/quality split is the most consequential number in an RFP. It's set before any supplier has written a word, and it can decide the winner more decisively than every evaluator's judgement combined. Yet teams often copy it from the last tender. This guide shows how to choose it deliberately, and how to test it before you publish.
Quick answer
Choose the price weight by asking how much suppliers can genuinely differ on quality for this contract. If the specification is tight and the product is standardised, price should carry most of the weight (60–80%). If outcomes depend on the supplier's people, method and judgement, quality should dominate (price at 20–40%). Before publishing, run a sensitivity test: score a realistic strong/expensive bid and a weak/cheap one at several splits, and check that the split you pick produces the result you'd defend. Pair any price-heavy split with a minimum quality threshold.
Where teams get the split wrong
- Inheriting it. "We always use 60/40" ignores that a cleaning contract and a systems integration carry very different quality risk.
- Setting a quality-heavy split, then scoring quality in a narrow band. If every bid scores 3 or 4, quality points barely differ and price decides anyway, whatever the published split.
- Price-heavy splits with no quality floor. At 70% price or above, a weak bid that's cheap enough can win. A threshold stops that.
- Not checking where the result flips. Two bids can swap rank across just a few points of price weight. If your chosen split sits right on that line, small scoring differences will decide the contract.
The framework: matching the split to the contract
| Contract profile | Examples | Quality risk | Typical price weight |
|---|---|---|---|
| Standardised, tightly specified | Commodities, office supplies, standard IT hardware | Low: the spec defines quality | 60–80%, or lowest price above a pass/fail spec |
| Defined service, some variation | Cleaning, security guarding, fleet leasing, parcel delivery | Medium: delivery model and staffing matter | 40–60% |
| Outcome-dependent service | Facilities management, managed IT services, logistics/3PL | High: mobilisation, people and continuous improvement drive results | 30–50% |
| Expertise-led or complex | Consulting, systems integration, creative agencies, R&D | Very high: the method is the product | 10–30%, or quality-first then negotiate |
The ranges above are starting points for discussion, not rules. Two questions should move you within or outside a range:
- How costly is a poor supplier relative to the price difference? If a failed mobilisation or a bad hire costs more than the gap between bids, weight quality up.
- Can you score quality reliably? If your criteria and scale definitions are weak, a heavy quality weight just amplifies noise. Fix the scale first.
In public procurement, the award basis is regulated. Under the UK Procurement Act 2023, contracts go to the "most advantageous tender" (section 19), and the authority must set an assessment methodology and indicate the criteria's relative importance as percentage weightings, a ranking or another description (section 23(3)). EU Directive 2014/24/EU uses the most economically advantageous tender (MEAT), identified on price or cost alone or on the best price/quality ratio (Article 67(2)). Weightings must be set out in the procurement documents, and can be given as a range with a maximum spread (Article 67(5)). The split is your choice within those rules; setting it out in advance isn't.
One published reference point comes from development finance. The World Bank's procurement regulations normally weight quality/cost at 90/10 for highly complex consulting assignments, 70–80/30–20 for moderate complexity, and 50–60/40–50 for routine work (Annex X, Table 2, September 2025 edition). That lines up with the bottom two rows of the table above.
How to choose and test your split, step by step
- Profile the contract using the table above and pick a starting split.
- Draft the quality criteria and scale (see RFP Scoring Matrix). You can't test a split without them.
- Build three or four test bids from realistic market knowledge: a premium supplier, a mid-market one, a low-cost one with visible gaps.
- Score them at several splits: 30, 40, 50, 60, 70 and 80% price.
- Find the crossover points: the price weights at which the ranking changes.
- Choose a split that's clearly inside the zone that produces the result you'd defend, not on the edge of a crossover.
- Add a quality threshold if your split is 50% price or more.
- Write the rationale down in the procurement file: profile, test results, chosen split, threshold. It's your answer if a bidder or auditor asks.
Illustrative example: where the winner flips
The scenario and numbers are invented to show the method. They're the same four bidders used in our RFP scoring matrix example: a three-year facilities-management contract.
Quality is scored out of 60 quality points at the base split (40% price); for the test it's converted to a 0–1 share so it can be re-weighted. Price uses lowest price ÷ bid price. No quality threshold is applied here, so you can see what happens without one.
| Bidder | Annual price | Price share (lowest ÷ bid) | Quality share (points ÷ 60) |
|---|---|---|---|
| A | $1,200,000 | 0.817 | 0.717 |
| B | $1,050,000 | 0.933 | 0.650 |
| C | $1,380,000 | 0.710 | 0.883 |
| D | $980,000 | 1.000 | 0.483 |
Total score = price weight × price share + quality weight × quality share:
| Price weight | A | B | C | D | Winner |
|---|---|---|---|---|---|
| 30% | 74.67 | 73.50 | 83.14 | 63.83 | C |
| 40% | 75.67 | 76.33 | 81.41 | 69.00 | C |
| 50% | 76.67 | 79.17 | 79.67 | 74.17 | C (by 0.51) |
| 60% | 77.67 | 82.00 | 77.94 | 79.33 | B |
| 70% | 78.67 | 84.83 | 76.21 | 84.50 | B (by 0.33) |
| 80% | 79.67 | 87.67 | 74.48 | 89.67 | D |
The crossover points:
- B overtakes C at about 51% price. Below that, the strongest bid wins; above it, the mid-priced, mid-quality bid does.
- D overtakes B at about 71.5% price. Above that, the cheapest bid wins despite scoring under half the available quality points.
What this tells the sourcing team:
- A 50/50 split is too close to call. C wins by half a point, so one evaluator scoring a criterion one point differently could flip the award. Pick 40% (C wins by over 5 points) or 60% (B wins by over 2), and know which outcome you're choosing.
- At 70% and above, you need a threshold. Without one, a bid with less than half the quality points can win or nearly win. With a 30-point threshold (half the quality points), D is excluded at every split.
- You can rerun this on your own bids. The free RFP scoring matrix template has a Sensitivity sheet that does this test automatically. Set its quality threshold to 0 to reproduce the table above.
- The split encodes a business judgement. Choosing 40% price says "C's stronger delivery approach and mobilisation plan are worth roughly $330,000 a year more than B's". Write that sentence in your rationale. If the business wouldn't say it out loud, the split is wrong.
Checklist
- Contract profiled (standardised → expertise-led) and starting split chosen
- Quality criteria and 0–5 scale definitions drafted before the split is tested
- Test bids scored at 30–80% price
- Crossover points identified, and the chosen split is clearly away from them
- Quality threshold set for any split of 50% price or higher
- Rationale written into the procurement file
- Split, criteria, weights and price formula published in the RFP
- Approach to abnormally low bids defined (especially for price-heavy splits)
When this approach needs adapting
- Lowest-price awards. For tightly specified goods, "lowest price among compliant bids" can be simpler and more transparent than a weighted split. The pass/fail specification does the quality work.
- Fixed-price or fixed-budget competitions. If the budget is published and bidders compete on what they deliver for it, price weight is effectively zero and quality is the whole evaluation.
- Consultant selection under development-bank rules. Funders such as the World Bank prescribe the selection method (e.g. quality- and cost-based selection, QCBS), a minimum technical score, and normal quality/cost ranges; departing from them needs the Bank's prior review. Follow the funder's procurement regulations, not a general rule of thumb.
- Price formulas that distort the split. The effective weight depends on the price formula as well as the headline split. With lowest ÷ bid, bids close in price earn similar points; with a range-based formula, the same price gap can produce a much bigger points gap. Test the formula and the split together.
How AI changes this step
Sensitivity testing used to mean a spreadsheet nobody had time to build. A general-purpose AI assistant can now generate test bids from a market brief, score them at every split and find the crossover points in minutes, so the split becomes a tested decision rather than a habit. It can also draft the rationale paragraph for the procurement file. Keep the judgement with people: the model can show where the result flips, but deciding what quality is worth paying for is a business call. Molecule One is building Qualo, an evaluation workspace that runs this kind of scenario test on live bid scores; it's currently in development.
Frequently asked questions
What is a good price/quality ratio for a tender? There isn't a universal one. Standardised goods often use 60–80% price; complex services and consulting often use 10–40%. Choose based on how much suppliers can differ on quality for this contract, then test the split before publishing.
Is 60/40 price/quality a standard? It's common, but not a standard. Whether 60/40 fits depends on the contract's quality risk and how reliably you can score quality.
What does MEAT mean in procurement? Most economically advantageous tender: the EU basis for award, which can be assessed on price or cost alone, or on a combination of price and quality criteria. The UK's Procurement Act 2023 uses "most advantageous tender".
Should I use a quality threshold? Yes, whenever price carries half the weight or more. It stops a cheap bid with weak quality from winning on price points alone.
Can the price weight be changed after bids are opened? No. The weighting should be fixed and published before bids are submitted. Changing it after seeing bids undermines fairness and, in public procurement, can expose the award to challenge.
Sources
- UK Procurement Act 2023, section 19: most advantageous tender; abnormally low tenders
- UK Procurement Act 2023, section 23: award criteria and relative importance
- Directive 2014/24/EU on public procurement, Articles 67 (award criteria) and 69 (abnormally low tenders)
- World Bank Procurement Regulations for IPF Borrowers, 7th edition (September 2025): QCBS (paragraph 7.3) and Annex X, Table 2
Further reading
- RFP Evaluation: The Complete Guide
- RFP Scoring Matrix: How to Build One
- AI for Vendor Evaluation
- How to Measure AI ROI in Procurement
Want help setting up evaluation methods your team can defend? See our procurement AI consulting.